Wikinger Phase 2

  • SECTOR: Offshore Renewables

Project Overview

Project Info

  • Date 15/07/18 – 18/07/18
  • Site Wikinger OWF
  • Vessel EDT Jane
  • Operations Boulder Relocation, Survey, Video and Inspection
  • UTROV® Tooling Used Tine Grab

Utility ROV Services were contracted by Adwen GmbH to conduct a second phase of boulder relocation operations on the Wikinger OWF.

The EDT Jane was mobilised with UTROV® System 2 to conduct a short work scope consisting of boulder and debris relocation and surveys around several WTGs. This included the removal of a small number of pre-determined targets. Clearance Certificates were issued for the area to allow a WTG installation vessel to access the areas and jack-up to perform a corrective campaign on the WTGs.

 

Work was performed within a live windfarm in close proximity to the WTGs, requiring close liaison with the field operator to ensure the required isolations were in place for select WTGs, whilst allowing the remainder of the field to continue operations unhindered.