Project
Rampion Phase 4
- SECTOR: Offshore Renewables
Project Overview
Project Info
- Date 27/11/17 – 15/01/18
- Site Rampion
- Vessel Siem N-Sea
- Operations Rock Bag Installation, Boulder Relocation
- UTROV® Tooling Used Rock Bag Deployment Tool, Tine Grab
Utility ROV Services were contracted by N-Sea to conduct boulder relocation and rock bag installation operations on the Rampion OWF.