Moray East Phase 3

  • SECTOR: Offshore Renewables

Project Overview

Project Info

  • Date 09/08/2020 – 03/09/2020
  • Site Moray East OWF
  • Vessel Olympic Triton
  • Operations Boulder Relocation
  • UTROV® Tooling Used Tine Grab
Utility ROV Services were contracted by Boskalis to conduct boulder relocation operations on the Inter Array Cable (IAC) Routes situated within Moray East Offshore Wind Farm, prior to cable installation. URS chartered the vessel, delivering full project management in addition to our standard provision of personnel and equipment.