Project
East Anglia One Phase 2
- SECTOR: Offshore Renewables
Project Overview
Project Info
- Date 30/04/20 - 18/05/20
- Site East Anglia One OWF
- Vessel Relume
- Operations Mattress Installation
- UTROV® Tooling Used Third-Party Mattress Frame
Utility ROV Services were contracted by Boskalis to perform mattress installation operations on the East Anglia One Offshore Wind Farm. Despite URS’ Mattress Installation Frame (MIF) being unavailable, a third-party mattress frame was sourced to allow the project scope to be completed.
A unique interface solution was designed in-house, allowing the mattress frame to be interfaced with the UTROV®. The mattress frame was modified by Utility ROV Services to enable full hydraulic functionality, thus achieving cycle times far superior to that of a traditional WROV.